Protester’s Own Discussion Questions Show It Had Information Forming Basis of Protest; GAO B-416989, CDO Technologies Inc.
Protest challenging the agency’s price realism and technical risk evaluation is dismissed as untimely, where the protester’s discussion questions suggested it was aware of the likely differences between its proposed core compensation and the awardee’s, and therefore could have filed its protest within 10 days of the debriefing.