Government Delays Before Modification to Extend Delivery Do Not Excuse Default; ASBCA No. 61027, Thunderstruck Signs
Appeal of the contracting officer’s termination for cause is denied, where the contractor failed to meet an oft-extended deadline to manufacture and install signs at an Air Force facility, and where previous delays caused by the government were immaterial once the parties agreed to a new extended deadline.