FPR Should Have Incorporated Information Provided in Response to Discussions; GAO B-412998, Ultra Electronics – 3 Phoenix, Inc.
Protest challenging the agency’s evaluation of the protester’s past performance is denied, where the agency reasonably considered information submitted by the protester acknowledging technical issues and cost overruns on its reference projects, and found its past performance provided low confidence despite one excellent rating on a relevant contract; and protest challenging the agency’s technical evaluation is denied, where the protester’s final proposal revision failed to incorporate information provided in response to discussions, despite the agency’s reminder of this requirement, and this missing information resulted in the assignment of a minor weakness.