GSA Claimed Contractor Was Liable for Damage Caused by a Burst Pipe. Contractor Said It Was an Act of God. What Did CBCA Think?March 8, 2024
You Can Ask the Agency to Clarify a Debriefing, But That Won’t Stop the Clock for an Agency ProtestMarch 8, 2024
Time for a Do-Over: GAO Finds Agency Mangled Discussions and Made Award to an Ineligible OfferorMarch 7, 2024
Contractor Said Agency’s Failure to Object to Non-Compliant Drawings Changed the Contract. CBCA Didn’t See It That Way.March 7, 2024
Agency Said It Didn’t Need to Strictly Follow Solicitation When Making Award. Why Did GAO Think This Argument Undermined the Entire Bid Protest System?March 6, 2024
If the Agency Didn’t Make a Representation About a Site’s Condition, It’s Difficult to Prove a Differing Site ConditionMarch 6, 2024
Contractor Asked ASBCA for Declaratory Relief. The Agency Then Terminated for Default. Could ASBCA Still Hear the Declaratory Appeal?March 6, 2024
If You Want the Agency to Consider Key Person’s Experience, Highlight It. Don’t Expect an Agency to Infer Experience from a Resume.March 5, 2024
Contractor Hadn’t Submitted a Claim for Its Affirmative Defense to a Termination. Did that Deprive ASBCA of Jurisdiction Over the Appeal?March 4, 2024
Solicitation Said Award Would Go to the Quote that Represented the “Best Value.” Did This Mean the Agency Had to Conduct a Tradeoff?March 1, 2024
Claim Asserted a Lump Sum Certain for Costs Under Two Different Contracts. Why Did ASBCA Let It Slide?March 1, 2024
Agencies Must Document a Proposal’s Strengths, Weaknesses, and Deficiencies. What’s an Agency Supposed to Do When a Proposal Is Merely Adequate?February 29, 2024
Federal Circuit Held Schedule Contract Incorporated Contractor’s Terms and Conditions. Now CBCA Has to Apply those Terms and Conditions.February 29, 2024