Protest Challenging AbilityOne Commission’s Decision to Implement Competitive Processes in Acquisitions Is Not Ripe; Melwood Horticultural Training Center, Inc. v. United States, COFC No. 20-758CDecember 15, 2020
CBCA Orders FEMA to Reimburse Local Utility for Disaster Relief Agreement Even Though Agreement Was Not Enforceable Contract; In the Matter of Florida Keys Electric Cooperative, CBCA 6822-FEMADecember 15, 2020
Contractor Waited Too Long To Get Paid; Appeal of Anis Avasta Construction Company, ASBCA No. 61926December 14, 2020
Protester’s Challenge to Agency’s Price Evaluation Premised on Glaring Mathematical Error; Tactical Network Corporation, GAO B-418962.2December 14, 2020
Court Finds that Solicitation’s Proposal Instructions Were Not Evaluation Criteria; Navarro Research and Engineering, Inc. v. United States, COFC No. 20-774CDecember 11, 2020
Agency Rightly Reject Vague Proposal that Parroted Back Solicitation Requirements; Systems Integration & Development, LLC, GAO B-427858.6 et al.December 11, 2020
CBCA Can’t Hear Appeal Filed One Day Late; JAF Supply, Inc. v. Department of Veterans Affairs, CBCA 6934December 11, 2020
Protester Prevails at COFC, Proves Agency Veered from Solicitation’s Evaluation Criteria; Bluewater Management Group, LLC. v. United States, COFC No. 20-1160CDecember 10, 2020
Protester’s Proposal Failed to Satisfy Requirement for “Armed Personal Protective Services”; Continuity Global Solutions, GAO B-419070December 10, 2020
It’s In There!: Alleged Unstated Criteria Encompassed by Stated Criteria; RiVidium Inc., GAO B-419096, B-419096.2December 10, 2020
SDVOSB That Didn’t Respond to Source Sought Notice Can’t Complain About Agency’s Set Aside Decision; HurtVet Subcontracting, LLC, GAO- B-419139December 10, 2020
Government Claim for Overpayment Not Untimely Even Though Government Discovered Contractor’s Non-Existent Accounting System More than Six Years Before Final Decision; Appeal of Doubleshot, Inc. ASBCA No. 61691December 9, 2020
GAO Finds Flaws in Evaluation But Concludes that Protester Was Not Prejudiced; Gunnison Consulting Group, Inc., GAO B-418876 et al.December 9, 2020
Agency Reasonably Downgraded Protester for Claiming Experience Developing a Program that Had Not Actually Been Developed; Analytica, LLC, GAO B-418966December 9, 2020
Agency’s Urgent Needs Justified Short-Term Sole-Source Contract; Summit Technologies, Inc., GAO B-419126, B-419126December 9, 2020
Providing Minimal Detail of Approach Is a Necessary But Not Sufficient Condition of Acceptable Proposal; Summit Technologies, LLC v. United States, COFC No. 20-946CDecember 8, 2020
While Weaknesses Assigned Under Different Subfactors Were Related, They Were Not Duplicative; NCI Information Systems, Inc., GAO B-418977December 8, 2020
Agency’s Best Value Comparison Did Not Improperly Reduce Competition to One Offeror; Trusted Mission Solutions, Inc., GAO B-418876.2December 8, 2020
Contractor Cannot Recover for Defective Estimates Under an IDIQ Contract; RocJoi Medical Imaging v. Department of Veterans Affairs, CBCA 6885December 8, 2020
Proposal Undone by Protester’s Humility; Cellco Partnership dba Verizon Wireless, GAO B-418155.4, B-418155.5December 7, 2020