Protester Unable to Demonstrate Adequacy of Its Accounting System; InterImage, Inc., GAO B-414104.47February 24, 2021
Agency Did Not Err in Calculating Protester’s Work Allocation; CMSoft, Inc. GAO B-419370February 24, 2021
Agency Reasonably Concluded that Typos in Proposal Created Concerns About Protester’s Quality Control; Epsilon, Inc., GAO B-419278, B-419278.2February 23, 2021
Agency Appropriately Assessed a Weakness to a Past Performance Reference that was Nine Months Behind Schedule; Bodell Construction Company, GAO B-419213, B-419213.2February 23, 2021
Protester Can’t Challenge Awardee’s Post-Award Transition Plan; Mission1st Group, Inc., GAO B-4129369.2February 23, 2021
Agency Entitled to Consider Experience of Key Personnel to Fill Gaps in Offering Entity’s Experience; Raven Operations, LLC, GAO B-419372February 23, 2021
No Problem with Agency Rejecting Proposal that “Lacked Most Components of an Offer”; Eskanos Enterprises, GAO B-419391February 23, 2021
ASBCA Denies Claim Premised on a Reading of the Film “The Magnificent Seven”; Appeals of GSC Construction, Inc. ASBCA Nos. 59402, 59601February 22, 2021
Talk to the Hand: Agency Not Required to Hold Discussions with Offeror Eliminated from Competition; Logistics Management Institute, GAO B-419219, B-419219.2February 22, 2021
Contractor Recovers Costs Incurred in Removing Larger-than-Expected Floating Fish Collector; Appeal of Central Diversified Contracting, LLC, ASBCA No. 62585February 22, 2021
Protester’s Subcontractor Failed to Submit Cost Data by Proposal Deadline, Agency Reasonably Refused to Consider Proposal; Kratos Defense & Rocket Support Services, Inc., GAO B-418172.2February 19, 2021
ASBCA Finds Government Subpoena Sought Immaterial and Duplicative Information, Quashes It; Appeals of Sand Point Services, LLC, ASBCA Nos. 61819, 61820February 19, 2021
Protest Challenging Corrective Action Is Premature; Cooper/Ports America, LLC, GAO B-419000.2February 19, 2021
“These Are Not the Droids You’re Looking For”: Protester Unable to Convince GAO that Language Mandating that a “Gravel Driveway Shall Be Provided” Did Not Actually Require a Driveway; KMK Construction, Inc., GAO B-418639.2February 18, 2021
Disagreement with Agency’s Take Does Not a Protest Make; KIRA Training Services, LLC, GAO B-419149.2, B-419149.3February 18, 2021
Protester Can’t Rely on Incumbency to Fill Gaps in Proposal; Stargates, Inc., GAO B-419349 et al.February 18, 2021
Challenge to Past Performance Evaluation Comes to Nothing; Trace Systems, Inc., GAO B-419323February 18, 2021
But I Said the Magic Words . . . Agency Entitled to Reject Proposal that Simply Restated Solicitation Requirements; Zolon PCS, LLC, GAO B-419283February 17, 2021
Contractor Obtains the Wrong Permit, Has to Redo the Work and Eat the Loss; Sarro & Associates, Inc. v. United States, COFC No. 19-691CFebruary 17, 2021
No Cardinal Change When the Final Product Is Not Much Different than that Specified By Contract; Appeals of Harry Pepper an Associates, Inc., ASBCA Nos. 62038 et al.February 17, 2021