News/Protests & Claims/Detailed Schedule Exceeded Solicitation Requirement, but That’s Not What Agency Wanted; GAO B-416836, Benaka Inc.
News·Protests & Claims Brief

Detailed Schedule Exceeded Solicitation Requirement, but That’s Not What Agency Wanted; GAO B-416836, Benaka Inc.

Protest that the agency misevaluated the protester’s proposal as technically unacceptable is denied, where the RFP clearly stated that construction schedules were limited to 30 activities or milestones, and the protester’s schedule significantly exceeded that number.

🔒 Members Only · Protests & Claims BriefYou’ve reached the member portion of this brief.Members read the full analysis and the source documents in every case digest, six days a week.
Not ready to join? Take the free Pub K Weekly digest.One email. Free. Top industry articles, the community calendar, and the latest job postings.