Contractor Failed to Inform Agency of Alleged Differing Site Conditions Upon Discovery; COFC No. 16-948 C, CKY Inc. v. United States
Claim seeking additional compensation on a construction contract due to differing site conditions is denied, where the agency’s pre-award communications and the contract advised offerors of the potential soil conditions at the project site, and where the contractor did not timely advise the government of the alleged differing site condition at the time it was discovered, but waited until it filed a request for equitable adjustment after the project was complete.