Lack of Certification Sinks Claim; ASBCA No. 60648, Appeal of Areyana Group of Construction Company
Appeal of the contracting officer’s denial of a claim is denied, where the appellant submitted multiple requests for equitable adjustment, but did not certify its final request as required for a claim exceeding $100,000, and where the CO’s issuance of a “final decision” did not convert the request into a claim.