Past Performance Questionnaire Contradicted Information in Protester’s Proposal; GAO B-413262.2, Williams Building Company Inc.
Protest challenging the agency’s evaluation of phase 1 proposal under a two-phase design-build selection process and decision to exclude the protester from phase 2 is denied, where the agency reasonably concluded the protester’s projects were only somewhat relevant to the requirement due to the difference in scope and value, and where the protester submitted a past performance questionnaire that contradicted the proposal’s statement about the protester’s experience constructing a certain type of facility; and where the agency reasonably concluded the protester’s proposal lacked sufficient detail about its scheduling processes, management approach, or overall understanding of the requirement.